Commercial jobs rarely end with the crew they started with — dispatch sends two more hands for the last stretch, a subcontractor covers the final hours. This release makes that reality first-class across the whole flow. Contractors now appear everywhere crew activities live: their own field on activities in the Crew App and on the work order, their own section on Dispatch's Assigned Team, and their own payroll under Expenses. Activity pickers now draw from the day's full roster — everyone available or working that day, not just the dispatched team. Activities can be added and deleted on the work order itself. And when a job is already complete, adding or editing an activity asks one question — apply these changes to Income as well? — so late entries land in billing and payroll without recalling anything.
1) On the work order's Dispatch tab, the Assigned Team now lists Contractors as their own section under Workers — each with their contractor type.

Assigned Team with a separate Contractors section
2) In the Crew App, Add and Edit Activity now carry a Contractors field beside Workers — both as chips, with the + to add and the × to remove.

Edit Activity in the Crew App: Workers and the new Contractors field, side by side
3) Tap the + on either field to add people on the spot:

Adding workers from the picker…

…and contractors the same way
4) The Workers dropdown is no longer limited to the dispatched team: it lists every worker available that day or assigned to any job that day, with this work order's own crew grouped under Assigned. Anyone unavailable that day is hidden.

The Workers dropdown: the day's full roster, with the job's own crew under Assigned
5) The Contractors dropdown works the same way — the day's available contractors, ready to join the activity.

The Contractors dropdown with the day's available contractors
6) The work order's Activities tab now has Add Activity (1) and a delete (2) on every activity — including ones posted from the Crew App.

Add Activity and per-activity delete on the work order's Activities tab
7) The Add Activity drawer carries the same Contractors field as the Crew App, with the same day-roster dropdowns.

Add Activity on the work order, Contractors included
8) Expenses → Payroll now shows Workers and Contractors as separate sections, each person with their actual hours and their own rate.

Payroll split into Workers and Contractors — hours × each person's own rate
9) The rates come from the profiles: the worker's Pay Rate under Settings → Resources → Workers…

The worker's hourly pay rate on their profile
10) …and the contractor's Pay Rate under Settings → Resources → Contractors.

The contractor's own pay rate — here $120/hr
11) A completed work order no longer ends the story. Change the status, open Add Activity (1–2), and enter the late activity — its own crew, its own contractor, its own start and end times, and Billable if it should reach the invoice (3).

Adding a manual activity on a completed work order — own crew, own times, billable
12) On Save, the system asks: “Activity has been updated. Do you want to apply these changes to Income as well?” Click Yes and the activity flows to the Income tab — and the people on it land in the payroll.

One question decides whether the change reaches Income
13) The result, end to end: the new activity sits beside the originals with its own crew and times…

The manually added Drive activity, with its own worker, contractor, and times
14) …Income picks up the corresponding line under Transportation Labor…

The Income line created from the manual activity
15) …and Payroll shows the added worker and contractor with their hours and rates.

Payroll after the sync: the late additions, costed correctly in both sections
16) Editing an existing activity asks the same question on Save — so corrections made after completion reach Income and payroll too, instead of living only on the activity record.

Edits to existing activities offer the same apply-to-Income choice
17) Deleting works the same way. Hit the delete on an activity card…

The delete action on an activity card
18) …and the prompt asks: “Activity has been deleted. Do you want to apply these changes to Income as well?” Yes removes everything that activity had put into Income and Expenses — its line items, quantities, and its workers' and contractors' payroll rows. No removes just the activity card, leaving Income and Expenses untouched.

Deleting an activity: Yes cleans it out of Income and Expenses too; No removes only the card
Contractors in crew activities, the day-roster pickers, work order activity management, the split payroll, and the apply-to-Income sync are live now — no setup beyond the pay rates on your worker and contractor profiles. The next time a job needs two more hands at 4 PM, add them where the work is. Built straight from how commercial jobs actually run; keep the feedback coming.